Commercial Unit, Newry
PROJECT OVERVIEW
MAC Construction were engaged by Granco Trucks Ltd to assist with constructing a purpose-built workshop at their headquarters in Newry.
Scope of Works:
Topsoil strip and reduced dig of 13,000 cubic meters disposed offsite.
Yard formation of 6000 square meters.
Shuttering and installation of pad foundations.
Design and Installation of main drainage, treatment plant and utilities including a series of drop manholes from 1.2 - 6m in depth.
Preparation and installation of reinforced concrete floor slab of 1100 square meters.
Installation of service pits and spillage bunds.
Our team worked diligently to ensure safety was at the forefront of project delivery whilst interfacing with other contractors. We proudly delivered a high quality result that was within time and budget.